GDE Change Evaluation Panel - TLCC-2 – Decision Memo / Barish, B ; GDE Change Evaluation Panel [ILC-MEMO-2010-004]
Proposal: "We propose to change the main linac tunnel configuration to one with only a single, accelerator-enclosure tunnel, thereby eliminating the support equipment tunnel proposed in the Reference Design. [...]
Fulltext: Download fulltextPDF; Download fulltextPS.GZ
Detailed record - Similar records
2010-10-25
17:25
Dubna Site Investigation - An Evaluation of a Proposed Site for the International Linear Collider near Dubna, Moscow Region, Russia / Dudarev, A ; Shirkov, G ; Trubnikov, G ; Sokolov, V ; et al [ILC-EDMS D*928865] [ILC-REPORT-2010-026]
In this Report we describe a study to consider siting the International Linear Collider (ILC) near Dubna, Russia, in the northern part of the Moscow region [...]
External link: Download fulltextFulltext
Detailed record - Similar records
2008-10-23
23:50
PM Monthly Reports - September 2008 / PM Office [ILC-INT-2008-025]
With this issue of the Technical Design Phase Monthly Report, you will find summary notes for the Group's monthly meetings (Main Linac Technology - Superconducting RF, Conventional Facilities and Siting, and Accelerator Systems), and a report from the Cost and Schedule Group (Peter Garbincius). [...]
Fulltext: Download fulltext
Detailed record - Similar records
2007-12-06
22:00
EDR Monthly Technical Reports - November 2007 / EDR Group Leaders [ILC-INT-2007-014]
Fulltext: Download fulltextPDF
Detailed record - Similar records
2007-11-20
20:39
Main Linac RF Power Distribution System Heat Load for the ILC Reference Design / Nantista, C.D. [ILC-NOTE-2007-035]
Fulltext: Download fulltextDOC
Detailed record - Similar records
2007-09-13
18:26
Report of the Engineering Design Planning Task Force / Ross, M ; Paterson, E ; Kephart, B ; Wolski, A ; et al [ILC-REPORT-2007-005]
The Engineering Design Planning task force was created by the ILC Executive Committee in March 2007 to assist it in adapting the organization of the GDE to support the creation of an Engineering Design Report (EDR). [...]
Fulltext: Download fulltextPDF
Detailed record - Similar records
2007-06-13
19:12
Minutes from DRIX Task Force Meeting 03 June 2007 / Tenenbaum, P. [ILC-INT-2007-011]
Fulltext: Download fulltextPDF
Detailed record - Similar records
2007-05-23
23:38
Representation of work spaces using a parametric model to support time-space conflicts analysis (A case study for time-space conflict analysis for the International Linear Collider project) / Kim J. ; Kim J.I. ; Kweon, H. [ILC-NOTE-2007-023]
Time-space conflict analysis has been used to improve work schedule in the construction industry. [...]
Fulltext: Download fulltextPDF
Detailed record - Similar records
2007-05-19
00:01
Damping Ring Injection and Extraction Region (DRIX) / Tenenbaum, P. [ILC-INT-2007-009]
Fulltext: Download fulltextPPT
Detailed record - Similar records
2007-05-09
22:35
Conventional Facilities Supporting Documentation for the ILC Reference Design Report / Kuchler, V [ILC-NOTE-2007-019]
External link: Download fulltextFulltext